Civil engineering works on developing a new road connecting the Goleniów Industrial Park and regional road no. 111 are approaching their end.
The contractor started putting an asphalt layer.
The embankment was reconstructed at a site strengthened with piling and the first asphalt layer placed. The road still requires the top surface layer to be developed, barriers fitted and stripes painted. Everything is expected to be completed this month.
The mayor received a report after an inspection by the party representing
the Westpomeranian Marshal’s Office. The report does not point to any irregularities which means that the project is considered correct. On Monday, the Mayor Robert Krupowicz signed the transfer of the final part of the grant for the road project supporting the operation of the GIP.